Key Takeaways
- UK–EU negotiations on the sanitary and phytosanitary (SPS) agreement concluded at the 20 November 2026 summit.
- Both sides aim to apply it from 1 March 2028, subject to their respective procedures. Keep using the requirements that apply to each movement today.
- Expected changes include fewer export health certificates for covered trade and removal of selected routine import checks. Scope, exceptions and transition arrangements still need confirmation.
- Map your goods, routes, documents and handovers now so that you can change operating instructions promptly when authoritative guidance is issued.
What is actually changing?
The UK–EU SPS agreement would bring the parties closer on sanitary and phytosanitary rules for animals, plants, their products, and food and feed safety. For a haulier, its practical significance lies in the documents a customer must obtain, the information a driver carries, and the possibility of a border inspection. It does not presently authorise you to remove a document from a load file or send a vehicle to a different inspection point.
The 20 November summit statement confirms that negotiations concluded and gives 1 March 2028 as the target date. The agreement still has to go through UK and EU procedures. Limited transition arrangements may apply, so use Defra’s implementation guidance to check when the change applies to your route.
This distinction matters for every booking. A customer might hear that a certificate will eventually disappear and conclude that a shipment can move without it next week. Your traffic office should instead check the requirements for the product and route on the movement date, then obtain confirmation from the party responsible for the goods. A planned implementation date is not a substitute for current official instructions.
Defra identifies hauliers and logistics providers among the businesses likely to be affected. The effect may extend beyond a straightforward Great Britain–EU export: Defra’s sector guidance says Great Britain, Northern Ireland and some domestic operations may be affected. Do not apply one generic lane rule to a mixed network. A driver taking an export load, a carrier collecting an EU import and an operator moving regulated plants can face different steps even when the commercial customer is the same.
Build a lane-by-lane SPS register
Start with the loads you actually carry, not a generic list of food businesses. For each regular service, record the product description supplied by the customer, the origin and destination, the border route, the responsible importer or exporter, and the present SPS paperwork. If the load mixes goods, record the regulated components separately. A pallet of ambient packaged food does not automatically follow the same process as chilled animal products or live plants.
Use a simple register that dispatchers can update without interpreting legislation. It should show who supplies each document, who confirms that it is valid, who makes any advance notification, and what the driver is expected to present or reference at each handover. The accountable owner should be named by role, not left as “the customer”. Where a freight forwarder, exporter and importer divide those tasks, make the division explicit in the booking instruction.
| Question for each lane | Record in the operating file | Why it matters |
|---|---|---|
| What goods are in the vehicle? | Customer description and regulated product groups | The agreement may not affect every product in the same way. |
| Where does the movement start and end? | Great Britain, EU, Northern Ireland and any transit legs | Requirements depend on route and jurisdiction. |
| Which documents apply now? | Current certificate, notification and plant-passport steps | You need a baseline before changing a process. |
| Who creates and checks them? | Exporter, importer, agent and carrier handovers | A removed requirement must not leave an ownership gap elsewhere. |
| Where can the load be held? | Current inspection and contingency instructions | Drivers need a clear route if authorities select a consignment. |
Review the register with the customers who own the goods. Ask them to confirm their commodity description and whether an official certificate, plant document or notification is currently required. Do not let a transport planner decide whether a food product is within a future agreement’s scope from a shorthand description on the manifest. If your business also handles ordinary customs declarations, keep those in a separate column: SPS changes do not by themselves abolish customs formalities.
A useful second pass is to identify where a requirement costs time rather than where it costs money. For example, a customer may arrange a certificate before loading, while your operation bears the delay if the documentation is not ready at collection. Another customer may handle advance notifications centrally, leaving your driver dependent on a reference at the gate. Map the point where each dependency can stop the vehicle. That gives you a practical readiness list before the new rules take effect.
Understand the likely benefits without treating them as current rules
Defra expects the agreed arrangements to remove export health certificates for most covered goods once they apply. Some live animal movements may still need other certification. Our guide to health certificates for UK food imports explains the paperwork that applies today. Its business information says an export health certificate can cost up to £200 per consignment. That is a stated upper example, not the fee for every load and not a saving you can promise to every customer. A shipment outside the final scope, or one moved before implementation, may still need its present certification.
The government also expects the removal of routine Port Health Authority border checks currently applying to imports of dairy, fish, eggs and red meat, according to Defra’s business information. “Routine” and “currently applying” are important qualifications. Do not translate that statement into “there will be no SPS inspections”. Authorities may retain targeted controls, and the final arrangements may specify exceptions, checks for particular risks or phased introductions.
Defra describes the prospect of trade resuming in some currently restricted products, including fresh sausages and burgers, certain shellfish and seed potatoes. That is a signal to watch for new customer demand, not permission to accept a previously prohibited load now. Before taking a new product group, obtain the customer’s written description and check the applicable official product and route guidance at the time. A commercial sales forecast should not become a traffic-office instruction.
For pricing, separate the possible removal of a customer’s certification cost from any transport saving. Less routine checking could improve predictability on a particular lane, but the target date is not yet an operative date and the guidance does not quantify journey-time improvements. Do not offer a fixed reduction in transit time on that basis. When the rules are published, compare actual dispatch and arrival data before changing service commitments.
Treat plants as a separate workstream
Plant movements have distinct planned changes. Defra’s sector guidance says phytosanitary certificates would no longer be required for movements to the EU and that EU plant passports would replace UK plant passports under the planned arrangements. The same guidance says an additional notification system would still be needed for high-risk plant imports from the EU. Those statements cannot be compressed into “plant paperwork ends”.
If you carry nursery stock, seed potatoes or other plants, list those loads separately from food products of animal origin. For chilled produce, record your cold chain controls alongside the plant health paperwork. Ask the customer who currently issues or obtains the phytosanitary certificate, where a passport is attached or referenced, and who would own any replacement process. Confirm whether the route is an export or import. A process described for goods moving to the EU is not automatically the process for goods arriving from the EU.
Your handover instructions should distinguish a certificate from a plant passport and a notification. They serve different purposes and may be handled by different people. A change to one requirement does not silently remove the others. Keep the present instructions in force until the relevant authorities issue operative guidance and the customer confirms its product-specific application.
High-risk plant imports need particular attention because Defra has expressly flagged a continuing notification system. If you arrange collections for several plant customers, avoid one blanket rule in the transport management system. Use a product-and-direction flag that can carry a different instruction for a high-risk import. Test any amended booking form with a real, anonymised lane before it becomes the default for all customers.
Keep Northern Ireland and mixed movements distinct
A Great Britain–EU operating note is not a complete Northern Ireland instruction. The summit statement says the benefits are intended to extend to Great Britain–Northern Ireland movements through the Windsor Framework. That does not settle how every Northern Ireland movement will operate. Check the relevant route-specific official guidance when a new rule is announced and ask the customer which party is responsible for compliance. Do not infer a Northern Ireland exemption or an identical process from the headline announcement.
Mixed movements deserve similar care. A vehicle may collect several consignments, only some of which are SPS-regulated or covered by a future simplification. The instruction for one consignment cannot be applied automatically to the whole trailer. Your load file should preserve a clear link between each consignment, its customer, its documents and any border reference. That lets a planner change a specific line without accidentally removing a requirement for another customer’s goods.
Where subcontractors operate a leg, send them the current route instruction and an effective date for any later revision. Keep a record of who received it. A new customer leaflet or industry news story is not enough to update a driver brief. The person controlling the vehicle needs the document list and contingency contact that apply to that journey, especially if a scheduled collection falls close to a future changeover date.
A readiness checklist for traffic and customer teams
You do not need to redesign the whole operation before the final rules are known. Defra says businesses are not expected to make detailed changes yet; they should understand potential effects, engage with updates and prepare. Give one owner responsibility for monitoring official updates and one owner responsibility for applying approved changes to operating instructions. A transport business with several depots should agree who signs off a network-wide change.
- Inventory the goods and lanes. Identify animal products, fish, plants, food and feed loads on each regular route. Keep the customer-provided product description with the booking record.
- Capture today’s control points. Record certificates, notifications, passports, inspections and driver references as they operate now. Include the person responsible for each step.
- Ask customers for scope decisions. Request their written assessment when final product coverage is published. The carrier should not invent a classification from a commercial product name.
- Watch authoritative updates. Monitor Defra’s implementation guidance and any route-specific notices from the competent authorities. Log the date and version of the instruction you use.
- Prepare controlled changes. Draft revised booking and driver-brief templates, but do not activate them until the relevant rules have an effective date and the customer confirms the applicable route.
- Brief exception handling. Decide who a driver calls when a document is missing or an authority directs a load for inspection. Keep that contact working during any transition.
Put a review date in the register rather than leaving it as a one-off exercise. A short periodic check can identify new product lines and changing customers if implementation slips. Record what changed and what did not. That audit trail is more useful than an undated statement that the business is “SPS ready”.
When an implementation notice is eventually issued, assess it in stages. First confirm the legal start date and which jurisdictions, products and movement directions it covers. Next confirm exceptions and any transition periods. Then change customer instructions, booking fields and driver briefs together. Finally, check the first live movements against the new process and correct any handover that fails. Until those stages are complete, retaining a current-process fallback is sensible operational control.
Frequently Asked Questions
Is the UK–EU SPS agreement already in force?
No. Negotiations have concluded and the target date is 1 March 2028, subject to UK and EU procedures. Continue to follow the requirements that apply to each shipment now.
Can a food exporter stop obtaining export health certificates?
Not yet. Defra expects certificates to cease for many covered movements once the agreement applies. Follow current product and route requirements until official instructions for the movement change.
Will all food imports avoid border inspection?
No such blanket change has been confirmed. Defra expects selected routine Port Health Authority checks on dairy, fish, eggs and red meat imports to be removed under the planned agreement. Targeted controls, exceptions and transition arrangements need to be checked in the final instructions.
What should a haulier do now?
Map its SPS loads and routes, document present certificate and notification handovers, and agree with customers who will decide whether each product is covered when the final rules arrive. Keep current driver instructions in force. Update them only after checking the effective official guidance for that lane.